top of page

Paraguay Renewable Hosting

202314

Host

Site Type

Greenfield

Power Operational

1

Contract Type

PPA

Sale Price without CAPEX

N/A

Est. CAPEX Datacenter Buildout

N/A

Est. total CAPEX contribution

N/A

#Hectare

N/A

Technical Plans Available

Yes

Region

Paraguay, Asuncion

All-in Power Price

5.14

$c/kwh

Operations & Maintenance & Hosting

Hosting provided by site developer

Est. CAPEX Power Production

N/A

Free Capacity at Substation

100

MW

Energy Mix

Hydro 100%

Seller Type

Mining company already operating in Paraguay

Est. CAPEX Power Delivery (incl. LV transf.)

N/A

Est. CAPEX Miners

Est. Total CAPEX/MW excl Miners

N/A

N/A

Permits & Regulations

Permitting complete, land purchased

Lease

N/A

Energy Type

Cooling Type

Hydro 100%

Air

Water Availability

N/A

Climate

Humid subtropical

Power Price Reduction Programs

N/A

Offer

Owner is developing a
12MW facility, with own funds
and is looking for:

1) Potential hosting clients at 6.2 - 6.5 $c/kwh all-in, or a mix between fixed fee and profit share (depending on volume and hardware efficiency). Set-up fee is 25-50 USD/miner depending on volume. Utility deposit 67,600 USD/MW, refundable at contract end. Minimum power 2MW. The terms are indicative.

2) Offering infrastructure development and farm operations. Infrastructure dev. for 150k-160k USD/MW depending on site. Including construction, suppliers and electricity.

Status

1MW operational

Timeline

Start Date of Mining Operation

2023

MW Phase 1

6

MW Phase 2

6

MW Phase 3

80 MW

MW Operational

1

Required Works for Phase 1

Buildout of 6 MW facility

Required Works for Phase 2

buildout of second 6 MW facility

Required Works for Phase 3

Capital needed

Buildout Time Phase 1

December 2023

Buildout Time Phase 2

March 2024

Buildout Time Phase 3

N/A

About the site

This project
is the development of a 12MW data center for bitcoin mining in 2
batches: (i) batch 1: 6MW for December 2023 and (ii) batch 2: 6MW for March 2024.
There will be 2 buildings of 6MW each , each building will have its own private line with
the substation. Electricity is supplied via private line. The photos show a comaparable site of the project developer in Paraguay.