top of page

Wisconsin Greenfield

202308

Invest

Site Type

Greenfield

Power Operational

0

Contract Type

Spot

Sale Price without CAPEX

$600 k

Est. CAPEX Datacenter Buildout

$750 k (land prep, transformers, switch gear)

Est. total CAPEX contribution

N/A

#Hectare

N/A

Technical Plans Available

No

Region

USA

All-in Power Price

4.5

$c/kwh

Operations & Maintenance & Hosting

Offer available

Est. CAPEX Power Production

0

Free Capacity at Substation

7.5

MW

Energy Mix

Mix

Seller Type

Mining company

Est. CAPEX Power Delivery (incl. LV transf.)

N/A

Est. CAPEX Miners

Est. Total CAPEX/MW excl Miners

N/A

$200 k/MW (7.5 MW, excl. containers)

Permits & Regulations

N/A

Lease

N/A

Energy Type

Cooling Type

Mix

Air hydro or immersion, high quality water available

Water Availability

High quality water available

Climate

Temperate

Power Price Reduction Programs

N/A

Offer

Land sale

Status

Land owned, agreements in place

Timeline

Start Date of Mining Operation

Not operational

MW Phase 1

7.5

MW Phase 2

25

MW Phase 3

N/A

MW Operational

0

Required Works for Phase 1

Set up mining on greenfield

Required Works for Phase 2

Depending on phase 1 setup, scaling the site

Required Works for Phase 3

N/A

Buildout Time Phase 1

2 months

Buildout Time Phase 2

N/A

Buildout Time Phase 3

N/A

About the site

This greenfield site has 7.5MW available at a CAPEX under $200k. The site can be ready within 3 months and a study for 25MW is ongoing. The site has access to spot power from the local utility provider. The main benefit of the site is its low cost, but no PPA is included.

Interested in this site? 

To:

Zeno Giacomuzzi (zgi@crypto-oxygen.com)

Product Manager

Subject:

Thanks for reaching out!

bottom of page